Manuel Magg, Project Director, Exyte
Driven by the global COVID-19 pandemic, the global chip industry is currently undergoing a phase in which demand far exceeds supply. For the coming years, market indicators predict a continued high demand, which global production capacities will be unable to satisfy. At the same time, capital projects in the semiconductor industry are continuously increasing not only in size and cost, but also in complexity. More and ever larger new semiconductor fabs (manufacturing facilities) are required to serve the growing market. The pressure for increased production capacity will constitute a huge challenge to the construction industry for years to come. It becomes clear, that methods traditionally used in the construction industry will not enable the breakthrough productivity shift required to meet the challenges at hand. What is urgently needed, is the understanding of the waste and losses produced during such complex, dynamic construction projects and of the immense improvement potentials often left unexploited.
For chip manufacturers, time to market is crucial. Research and development on a new manufacturing generation is often still in progress during the construction of the respective high volume manufacturing fab. Resulting in continuous changes in basic project requirements while a fab is already under design and even construction. These dynamic conditions, together with the high technical complexity, large project size as well as schedule pressure, are what can generate huge amounts of waste, delays and reworks, which often cause significant cost and schedule overruns.
Large capital projects always require early scope development, strategic pre-planning, and adequate resources in order to be delivered successfully. Digitized processes and a full shift towards virtual design and construction will advance future project performances additionally. However, with multiple dynamically interconnected systems, semiconductor construction projects will still rely to a high degree on human intelligence. Leadership, motivation, mind setting, coaching, networking, decision-making, continuous learning or risk evaluation are such crucial human interactions. The best way to optimize these human interactions and to achieve a state of high performance is by establishing a team with an agile mindset and team culture as well as an agile project execution model.
Traditionally, construction management of large projects has always strongly relied on hierarchical power, command chains and on siloed organizations. Instead, we need to strive for a team culture, where servant leadership provides and maintains an overarching vision to the whole project team, where all team members feel empowered and secure to raise concerns, regardless of their position in the organization chart, and where human interaction help create advanced alignment. Where every project team member commits to timely decision-making, rapid delivery and review cycles, frequent customer engagement and feedback as well as continuous improvement. Project leadership has to initiate, charter, foster and role model this kind of project team culture.
One of the key features of such agile construction project organization is the self-organized work-group team. These teams will be accountable for the delivery of a certain scope component (e.g. the Ultra-Pure-Water System, the Cleanroom) from basis of design throughout the project life cycle until hand-over to the owner. These work group teams consist of a Team Lead, or Product Owner in scrum terms, who defines and manages the requirements and the scope of work; a design lead engineer; a construction manager; one or several trade representatives and an owner’s representative. Ideally, a Scrum Master guides the team towards efficient sprint execution and delivery. Each work group team consists of members, who collectively possess all skills required to deliver their scope of work, and who are fully empowered to make decisions.
To achieve a swarm intelligent project team, it is important that the overall project goals are broken down into sub-goals for each work group team. For an overall schedule milestone, each work group team will receive a requirement catalogue clearly defining the team’s deliverables to achieve the project milestone. Similarly, when the project has an overall target cost, each work group team will receive and commit to the target cost for their respective scope of work. All work group team’s target costs will add up to the total project target cost. The teams regularly report their actual cost forecast versus their target cost, using key indicators and visual displays to drive overall transparency.
We Need To Strive For A Team Culture, Where Servant Leadership Provides And Maintains An Overarching Vision To The Whole Project Team, Where All Team Members Feel Empowered And Secure
Coordination between these teams has to happen proactively and self-initiative. Daily huddles, face-to-face conversations and visualization in a collaboration room help foster interdisciplinary coordination. The project team will turn into a highly interconnected network of independently working, but continuously communicating cells. Changes, risks or deviations from plan are being collaboratively discussed between the owner, designer, general contractor and trade representatives within the work group teams. For this purpose, it is essential that the owner’s representatives engage regularly with the work group teams and attend daily huddles and meetings. Fast production of design deliverables and incremental reviews with the owner’s representative ensure the design and construction progress will stay aligned with the owner’s requirements and expectations. All team members are encouraged to raise significant risks or concerns immediately to the project leadership, at which level aligned strategies for risk mitigation are being developed and communicated.
When construction teams are stuck in silo thinking, blame culture and toxic behavior, drastic performance drops and major cost and schedule overruns are almost unavoidable. An agile project set-up, together with a respectful team culture are essential to unlock the productivity potentials required for project success. The advances of lean and scrum offer great help to overcome the challenges and to achieve such team culture. Experience suggests an implementation of a combined last planner and scrum in construction execution model for upcoming fab construction projects. The challenges ahead in the chip industry are enormous, but by utilizing advanced agile frameworks, delivering leading edge semiconductor fabs will remain one of the most exciting journeys in the engineering world.
Weekly Brief
I agree We use cookies on this website to enhance your user experience. By clicking any link on this page you are giving your consent for us to set cookies. More info
Read Also
New Hr Capabilities To Face Evolving Technologies
Strengthening The Compliance Fortress In The Banking Sector
Navigating Legal Challenges By Adapting To Technological Shifts
Compliance In The Medtech Industry
How Can The American Trade Finance Companies Manage Present (And Future?) Chinese Mineral Export Control Measures?
Optimizing Customer Experiences Through Data-Driven Strategies
Customer-Oriented And Compliance Mindsets In Claims Management
Optimizing Business Efficiency with a Multi-Disciplinary Legal Operations Team